Builder's quote example — patio, retaining wall & steps

A worked example of how a builder prices external groundworks: excavate and cart away, pour foundations, build a retaining wall, lay a sub-base and 30 m² of porcelain paving with steps — including the prelims most quotes forget.

The job

Transform a sloping rear garden: excavate and remove spoil, pour a foundation and build a 900mm block retaining wall, then lay a compacted sub-base and 30 m² of porcelain paving with three formed steps. This is a groundworks-led building quote — muck-away, sub-base and prelims are where these jobs are won or lost.

Unlike a room refurb, external work carries real plant, spoil-removal and welfare costs. Pricing them openly (as prelims) keeps the headline rate honest.

The worked quote

ItemQty / basisAmount
Set up, protect site, excavate & cart away spoilEnabling£780.00
Concrete trench-fill foundation to retaining wallFoundation£640.00
Build retaining wall in facing block12 m²£1,320.00
Supply, lay & compact MOT Type 1 sub-base30 m²£560.00
Lay 100mm concrete base / bedding30 m²£720.00
Supply porcelain paving (30 m² + waste)Materials£1,050.00
Lay porcelain paving — labour30 m²£1,200.00
Form & pave steps3 no.£480.00
Point, seal & clean downFinishing£260.00
Prelims — welfare, skips, plant & mini-digger hireProject£520.00
Subtotal (ex VAT)£7,530.00
VAT @ 20%£1,506.00
Total£9,036.00

How the pricing works

  • Muck-away is priced, not swallowed

    Excavation and carting spoil away is a real cost with real skip and haulage charges. It's the number that most often gets forgotten and eats the margin.

  • Prelims are a line

    Welfare, skips and plant hire (the mini-digger and dumper) total £520 here. On external work these are unavoidable — quoting them stops the price looking artificially low then creeping up.

  • Sub-base separates from paving

    The base build-up (MOT sub-base and concrete) is priced apart from the paving. A patio is only as good as what's under it, and customers should see that work valued.

  • Materials and labour split

    Paving supply (£1,050) and paving labour (£1,200) are separate lines, so a change of slab changes one figure, not the whole job.

What's excluded

External groundworks border other work — set the edges of scope clearly.

  • Drainage alterations, soakaways or connecting to existing surface water
  • Electrical work for external lighting or sockets
  • Fencing, gates, planting or turfing
  • Removal of unforeseen obstructions (old foundations, tree roots) below ground

Build this quote in ProQuoter

Builder's groundworks quote in ProQuoter
Screenshot of the live ProQuoter app — not a mock-up or stock image.

FAQ

How much does a builder charge for a patio and retaining wall?
This worked example prices 30 m² of porcelain paving with a 12 m² retaining wall and steps at £7,530 ex VAT (£9,036 inc VAT), including groundworks and prelims. Size, access, ground conditions and slab choice move the figure. Figures are an illustrative UK example for guidance only — set your own rates, materials and margins in ProQuoter.
What are prelims in a builder's quote?
Preliminaries are the project-wide costs that aren't a specific trade item — welfare, skips, plant hire, site set-up and protection. Here they total £520. Leaving them out makes a quote look cheaper but almost guarantees a shortfall.
Should a builder's quote include muck away?
Yes. Excavation without carting the spoil away is only half the job. This example prices set-up, excavation and disposal together at £780 — the removal cost is real and belongs on the quote.
Do builders charge VAT?
VAT-registered builders charge 20% on most domestic work (shown here as £1,506). Some new-build and certain conversions are zero- or reduced-rated — but a standard patio and wall are standard-rated.