Skip to main content

Plumber quote example — replacing a bathroom suite

A worked example of how a plumber prices a suite swap: remove the old WC, basin and bath, install new sanitaryware, adjust the pipework and commission — with a clear sanitaryware allowance and VAT.

The job

Rip out a tired bathroom suite and install a new one in the same layout: close-coupled WC, vanity basin, bath with a thermostatic bar shower. No tiling and no building work — this is a plumbing quote, with the sanitaryware carried as a provisional allowance the customer can trade up or down.

Because the sanitaryware is a customer choice, it is priced as a PC (prime cost) allowance rather than a fixed figure — the labour to fit it stays the same whatever they pick.

The worked quote

ItemBasisAmount
Isolate, drain down & remove existing suiteLabour£180.00
Install close-coupled WC & connectLabour£120.00
Install vanity unit & basin, connect waste and suppliesLabour£160.00
Install bath, panel & thermostatic bar showerLabour£260.00
Alter & extend pipework for new connections (first fix)Labour£220.00
Fit new isolation valves & flexi connectorsLabour + parts£80.00
Sanitaryware — WC, basin/vanity, bath, shower, wastes (PC allowance)Provisional£1,150.00
Test, commission & sealLabour£90.00
Subtotal (ex VAT)£2,260.00
VAT @ 20%£452.00
Total£2,712.00

How the pricing works

  • Labour per fixture

    Each fixture is a line so the customer sees where the time goes — and if they drop the bath for a shower tray, you adjust one number, not the whole quote.

  • A PC allowance for sanitaryware

    The £1,150 is a provisional allowance. If the customer chooses a £1,400 suite, the difference is added; a cheaper suite reduces it. The fitting labour is unaffected.

  • First-fix adjustments included

    Pipework rarely lines up perfectly with new units. Pricing an allowance for altering supplies and wastes avoids a mid-job variation.

  • Commissioning matters

    Testing and sealing is a real, chargeable step — it's what stops a callback for a weeping compression joint two weeks later.

What's excluded

A plumbing suite swap sits alongside other trades — be explicit about where your scope ends.

  • Tiling, flooring and making good walls
  • Electrical work — shaver socket, extractor fan, lighting or an electric shower circuit
  • Plastering or boarding
  • Removing existing tiling or altering the room layout

Build this quote in ProQuoter

Plumbing quote in the ProQuoter quote builder
Screenshot of the live ProQuoter app — not a mock-up or stock image.

FAQ

How much does it cost to replace a bathroom suite?
This worked example prices a like-for-like suite swap at £2,260 ex VAT (£2,712 inc VAT), including a £1,150 sanitaryware allowance. Strip out the allowance and the plumbing labour alone is £1,110. Figures are an illustrative UK example for guidance only — set your own rates, materials and margins in ProQuoter.
Does a plumber's quote include the sanitaryware?
It can, but it's cleaner to show it as a separate PC (prime cost) allowance so the customer can choose their own fixtures without reworking your labour price. This example carries £1,150 as a provisional allowance.
What is a PC sum or provisional allowance?
A prime cost (PC) sum is a placeholder for an item the customer hasn't chosen yet — here, the sanitaryware. You quote a sensible allowance, then adjust the final invoice to the actual cost once they've picked.
Do plumbers charge VAT?
If VAT registered, yes — 20% on the net, shown as a separate line here (£452). Domestic plumbing is standard-rated in most cases; only specific energy-saving installations attract a reduced rate.